| Project Name | Contractor | Contract Date | Duration (Weeks) | Expected Completion | Revised Completion | Contract Amount | Progress Payment | Balance | Financial Status | Physical Status | Contractual No. | Actual Connections | Financier | Project Status |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Ntina:Sekhahlela | B&G | 13-May-24 | 26 | 18-Nov-24 | 31-May-25 | M8,555,514.31 | M5,793,924.21 | M2,761,590.10 | 68% | 100% | 180 | GoL | Completed | |
| Mokema | B&G | 13-May-24 | 34 | 13-Jan-25 | 15-May-25 | M22,652,307.52 | M14,958,721.28 | M7,693,586.24 | 66% | 100% | 830 | GoL | Completed | |
| Makoaela: Berea | Highlands | 17-Oct-24 | 12 | 16-Jan-25 | 23-May-25 | M2,473,096.19 | M2,421,691.65 | M51,404.54 | 98% | 100% | 101 | GoL | Completed | |
| Sekhutlong: Berea | Highlands | 17-Oct-24 | 16 | 13-Feb-25 | 16-May-25 | M3,321,175.28 | M2,531,733.66 | M789,441.62 | 76% | 100% | 74 | GoL | Completed | |
| Aupolasi: Qacha's Nek | Powertech | 17-Oct-24 | 12 | 16-Jan-25 | 30-May-25 | M2,259,659.66 | M1,920,728.93 | M1,902,348.74 | 85% | 100% | 50 | GoL | Completed | |
| Mohlakeng: Thaba Tseka | Jimmy | 24-Oct-24 | 36 | 10-Jul-25 | 29-Aug-25 | M15,828,820.52 | M9,369,832.23 | M6,458,988.29 | 59% | 91% | 400 | GoL | On Going | |
| Mofolaneng: Mokhotlong | K.R | 23-Oct-24 | 46 | 17-Sep-25 | M12,719,024.15 | M9,140,624.18 | M3,578,399.97 | 72% | 77% | 300 | GoL | On Going | ||
| Ha Kobotsoeu: Mohale's Hoek | Powertech | 23-Oct-24 | 24 | 16-Apr-25 | 30-Sep-25 | M10,468,487.78 | M6,423,796.14 | M4,044,691.64 | 61% | 62% | 350 | GoL | On Going | |
| Liqoabing (Leralleng): Maseru | LSP Construction | 31-Oct-24 | 24 | 24-Apr-25 | 31-Aug-25 | M20,265,007.08 | M5,067,341.83 | M15,197,665.25 | 25% | 65% | 530 | GoL | On Going | |
| Mphaki Sekake Line: Mohale's Hoek | B&G | 18-Oct-24 | 48 | 26-Sep-25 | M24,175,198.10 | M13,472,741.58 | M10,702,456.52 | 56% | 56% | N/A | GoL | On Going | ||
| Tlali, Mapotsane: Mohale's Hoek | Lesehe Construction | 26-Feb-25 | 52 | 4-Mar-26 | M21,547,050.12 | M8,978,042.19 | M12,569,007.93 | 42% | 100% | 450 | GoL | On Going | ||
| Tsaba - Lira: Leribe | LR Construction | 29-Jan-25 | 20 | 25-Jun-25 | 17-Sep-25 | M8,014,810.50 | M4,543,853.57 | M3,470,956.93 | 57% | 50% | 230 | GoL | On Going | |
| Makaung: Mafeteng | Jimmy | 30-Jan-25 | 34 | 2-Oct-25 | M21,791,192.59 | M5,094,849.60 | M16,696,342.99 | 23% | 68% | 510 | GoL | On Going | ||
| Ha Motanyane: Mafeteng | Selemela Construction | 28-Feb-25 | 42 | 26-Dec-25 | M25,990,621.73 | M7,076,398.66 | M18,914,223.07 | 27% | 74% | 456 | GoL | On Going | ||
| Ha Thabo:Thaba-Tseka | Khalanyane Electrics | 11-Jul-25 | 18 | 21-Nov-25 | M4,601,184.50 | M0.00 | M4,601,184.50 | 0% | 0% | 120 | GoL | On Going | ||
| Ha Raliemere: Mafeteng | Lead On Technologies | 25-Jun-25 | 36 | 11-Mar-26 | M11,184,405.35 | M0.00 | M11,184,405.35 | 0% | 0% | 252 | GoL | On Going | ||
| Tsime: Botha-Bothe | Power Factor | 25-Jun-25 | 24 | 17-Dec-25 | M16,555,535.03 | M1,030,860.00 | M15,524,675.03 | 0% | 0% | 500 | GoL | On Going | ||
| Lihlabeng, Ha Likariki: Leribe | The Village | 25-Jun-25 | 46 | 20-May-26 | M16,038,521.65 | M0.00 | M16,038,521.65 | 0% | 0% | 570 | GoL | On Going | ||
| Mpiti Sekake (T&D): Qacha'snek | Selemela Construction | M12,097,944.93 | M0.00 | M12,097,944.93 | 0% | 0% | GoL | Contract drafting | ||||||
| Likhutlong: Botha-Bothe | Selemela Construction | M14,567,165.69 | M0.00 | M14,567,165.69 | 0% | 0% | GoL | Contract drafting | ||||||
| Kolo, Ha Ntsie, Ha Mofolo: Mafeteng | KR Holdings | 7-Aug-25 | M33,174,653.81 | M0.00 | M33,174,653.81 | 0% | 0% | GoL | Contract drafting | |||||
| Ntsokoane and Choko | LSP Construction | 1-Aug-25 | M19,061,568.14 | M0.00 | M19,061,568.14 | 0% | 0% | GoL | On Going | |||||
| Ha Lesoiti | Nutra Investment | 31-Jul-25 | M10,100,033.85 | M0.00 | M10,100,033.85 | 0% | 0% | GoL | On Going | |||||
| Ha Matsie | Adjudication | M0.00 | M0.00 | M0.00 | 0% | 0% | GoL | Under Procurement | ||||||
| Tlokoeng: Mokhotlong | Adjudication | M0.00 | M0.00 | M0.00 | 0% | 0% | GoL | Under Procurement | ||||||
| Thaba Khupa: Maseru | Pending evaluation | M0.00 | M0.00 | M0.00 | 0% | 0% | GoL | Under Procurement | ||||||
| Lifotholeng, Ha Tebalete: Berea | Pending evaluation | M0.00 | M0.00 | M0.00 | 0% | 0% | GoL | Under Procurement | ||||||
| Phutha-Lichaba: Quthing | Pending evaluation | M0.00 | M0.00 | M0.00 | 0% | 0% | GoL | Under design | ||||||
| Ha Ntho: Quthing | Pending evaluation | M0.00 | M0.00 | M0.00 | 0% | 0% | GoL | Under design | ||||||
| Bochebeletsane, Ha-Letuka, Ha Mokotoane: Thaba Tseka | Pending evaluation | M0.00 | M0.00 | M0.00 | 0% | 0% | GoL | Under Procurement | ||||||
| Mokhorong (Roma): Maseru | Tender Stage:Bids sent to Bidders | M0.00 | M0.00 | M0.00 | 0% | 0% | GoL | Under Procurement | ||||||
| Thaba-Phatsoa: Berea | Tender Stage:Bids sent to Bidders | M0.00 | M0.00 | M0.00 | 0% | 0% | GoL | Under Procurement | ||||||
| Ha-Napo: Berea | Tender Stage:Bids sent to Bidders | M0.00 | M0.00 | M0.00 | 0% | 0% | GoL | Under Procurement | ||||||
| Bethel,Malephane(Phamong): Quthing | Tender Stage:Bids sent to Bidders | M0.00 | M0.00 | M0.00 | 0% | 0% | GoL | Under Procurement | ||||||
| Ha-Nkhoboto | Design stage | M0.00 | M0.00 | M0.00 | 0% | 0% | GoL | Under Procurement | ||||||
| Khoiting: Mohaleshoek | Tender Stage:Bids sent to Bidders | M0.00 | M0.00 | M0.00 | 0% | 0% | GoL | Under Procurement | ||||||
| Bulu-Bulu(Mekaling): Mohaleshoek | Tender Stage:Bids sent to Bidders | M0.00 | M0.00 | M0.00 | 0% | 0% | GoL | Under design | ||||||
| Thuathe Villages:Ha-Motsumi,Ha-Mafaesa, Ha-Ralimo: Berea | Tender Stage:Bids sent to Bidders | M0.00 | M0.00 | M0.00 | 0% | 0% | GoL | Under Procurement | ||||||
| Cana(Sebalabala):Berea | Tender Stage:Bids sent to Bidders | M0.00 | M0.00 | M0.00 | 0% | 0% | GoL | Under Procurement | ||||||
| Ha-Selomo: Butha-Buthe | Design stage | M0.00 | M0.00 | M0.00 | 0% | 0% | GoL | Under design | ||||||
| Linakeng: Butha-Buthe | Design stage | M0.00 | M0.00 | M0.00 | 0% | 0% | GoL | Under design | ||||||
| Ha-Mpharoane: Butha-Buthe | Design stage | M0.00 | M0.00 | M0.00 | 0% | 0% | GoL | Under Procurement | ||||||
| Pobeng: Leribe | Design stage | M0.00 | M0.00 | M0.00 | 0% | 0% | GoL | Under Procurement | ||||||
| Ha-Nyane:Leribe | Design stage | M0.00 | M0.00 | M0.00 | 0% | 0% | GoL | Under Procurement | ||||||
| Thaba-Lesoba:Leribe | Design stage | M0.00 | M0.00 | M0.00 | 0% | 0% | GoL | Under Procurement | ||||||
| Menkhoaneng:Leribe | Design stage | M0.00 | M0.00 | M0.00 | 0% | 0% | GoL | Under design | ||||||
| Ha-Mechak:Maseru | Design stage | M0.00 | M0.00 | M0.00 | 0% | 0% | GoL | Under Procurement | ||||||
| Ha-Motanyane:Maseru | Design stage | M0.00 | M0.00 | M0.00 | 0% | 0% | GoL | Under Procurement | ||||||
| Majapereng: Mohaleshoek | Design stage | M0.00 | M0.00 | M0.00 | 0% | 0% | GoL | Under design | ||||||
| Pontseng: Quthing | Design stage | M0.00 | M0.00 | M0.00 | 0% | 0% | GoL | Under design | ||||||
| Ha Mathabela: Quthing | Design stage | M0.00 | M0.00 | M0.00 | 0% | 0% | GoL | Under Procurement | ||||||
| Ha-Mosue: Quthing | Design stage | M0.00 | M0.00 | M0.00 | 0% | 0% | GoL | Under Procurement | ||||||
| Ha-Letuka,Ha Mokotoane: Thaba-Tseka | Tender Stage:Bids closed | M0.00 | M0.00 | M0.00 | 0% | 0% | GoL | Under Procurement | ||||||
| Ha-Mohlehli:Mafeteng | Tender Stage:Bids sent to Bidders | M0.00 | M0.00 | M0.00 | 0% | 0% | GoL | Under Procurement | ||||||
| Sekanteng: Mafeteng | Design stage | M0.00 | M0.00 | M0.00 | 0% | 0% | GoL | Under design | ||||||
| Ha-Thoko: Maseru | Design stage | M0.00 | M0.00 | M0.00 | 0% | 0% | GoL | Under Procurement | ||||||
| Ha-Tseka: Maseru | Design stage | M0.00 | M0.00 | M0.00 | 0% | 0% | GoL | Under Procurement | ||||||
| Ha-Mapeshoane:Berea | Design stage | M0.00 | M0.00 | M0.00 | 0% | 0% | GoL | Under design | ||||||
| Linakeng: Butha-Buthe | Design stage | M0.00 | M0.00 | M0.00 | 0% | 0% | GoL | Under design | ||||||
| Ha-Matanki:Berea | Design stage | M0.00 | M0.00 | M0.00 | 0% | 0% | GoL | Under Procurement | ||||||
| Ha-Lehlohonolo:Berea | Design stage | M0.00 | M0.00 | M0.00 | 0% | 0% | GoL | Under Procurement | ||||||
| Ha-Letjama:Mokhotlong | Design stage | M0.00 | M0.00 | M0.00 | 0% | 0% | GoL | Under Procurement | ||||||
| Letlapeng:Mohaleshoek | Design stage | M0.00 | M0.00 | M0.00 | 0% | 0% | GoL | Under Procurement | ||||||
| Sekoaing Pumping System | T&D Project | M0.00 | M0.00 | M0.00 | 0% | 0% | GoL | Under Procurement | ||||||
| Mohale villages | Tough Services | 26-Feb-25 | 60 | 29-Apr-26 | M17,834,751.23 | M0.00 | M17,834,751.23 | 0% | 35% | 198 | LHDA | On Going | ||
| Ha-Letsie | Lesehe | 42 | 27-Oct-00 | M13,377,739.50 | M0.00 | M13,377,739.50 | 0% | 0% | 150 | LHDA | Contractor to be negotiated | |||
| Total Signed | M414,204,063.68 | M135,307,118.34 | M280,460,363.35 | 7385 | 1247 | |||||||||
| Total Awarded but Not Signed | M122,718,290.59 | |||||||||||||
| 17% | ||||||||||||||